Please see below, update from North Yorkshire Council Highways on the resurfacing work:
As you may have observed, the scheme is progressing well with the binder course reinstated through to the Mark Lane junction. The laying of the surface course commenced yesterday and it is envisaged that phase 1 will be completed Wednesday with the team moving north to Phase 2 on Thursday morning (Mark Lane to north end of village).
Scheduled bus routes are being diverted for phase 2 with a temporary stop sited at Deighton Road, Wetherby opposite the Wetherby Road junction, as below.